<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Archívy Via Carpatia - Doprava.org</title>
	<atom:link href="https://www.doprava.org/znacka/via-carpatia/feed/" rel="self" type="application/rss+xml" />
	<link>https://www.doprava.org/znacka/via-carpatia/</link>
	<description>Všetko, čo sa hýbe. Správy, analýzy, trendy</description>
	<lastBuildDate>Thu, 05 Nov 2026 22:00:26 +0000</lastBuildDate>
	<language>sk-SK</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	<generator>https://wordpress.org/?v=7.1.4</generator>

<image>
	<url>https://www.doprava.org/wp-content/uploads/2026/02/cropped-D-32x32.png</url>
	<title>Archívy Via Carpatia - Doprava.org</title>
	<link>https://www.doprava.org/znacka/via-carpatia/</link>
	<width>32</width>
	<height>32</height>
</image> 
	<item>
		<title>Poliaci dokončujú cestu Via Carpatia. Pozrite sa, ako vyzerá</title>
		<link>https://www.doprava.org/poliaci-dokoncuju-cestu-via-carpatia-pozrite-sa-ako-vyzera/</link>
		
		<dc:creator><![CDATA[Šimon Brtáň]]></dc:creator>
		<pubDate>Fri, 06 Nov 2026 16:00:00 +0000</pubDate>
				<category><![CDATA[Cesty]]></category>
		<category><![CDATA[cesty]]></category>
		<category><![CDATA[diaľnice]]></category>
		<category><![CDATA[Poľsko]]></category>
		<category><![CDATA[rýchlostné cesty]]></category>
		<category><![CDATA[Via Carpatia]]></category>
		<guid isPermaLink="false">https://www.doprava.org/?p=4842</guid>

					<description><![CDATA[<p>Poľsko pokračuje vo výstavbe koridoru Via Carpatia. Pri Białystoku pribudlo prepojenie rýchlostných ciest S19 a S8, na juhu krajiny vznikajú technicky náročné estakády a tunely. Na najvyššej cestnej estakáde v Poľsku už dokončili betónovanie nosnej konštrukcie pre jeden smer premávky. Výstavbu smerom k Slovensku však sprevádzajú aj komplikácie a výmena zhotoviteľa. Via Carpatia je medzinárodný [&#8230;]</p>
<p>Článok <a href="https://www.doprava.org/poliaci-dokoncuju-cestu-via-carpatia-pozrite-sa-ako-vyzera/">Poliaci dokončujú cestu Via Carpatia. Pozrite sa, ako vyzerá</a> je zobrazený ako prvý na <a href="https://www.doprava.org">Doprava.org</a>.</p>
]]></description>
										<content:encoded><![CDATA[
<p class="wp-block-paragraph">Poľsko pokračuje vo výstavbe koridoru Via Carpatia. Pri Białystoku pribudlo prepojenie rýchlostných ciest S19 a S8, na juhu krajiny vznikajú technicky náročné estakády a tunely. Na najvyššej cestnej estakáde v Poľsku už dokončili betónovanie nosnej konštrukcie pre jeden smer premávky. Výstavbu smerom k Slovensku však sprevádzajú aj komplikácie a výmena zhotoviteľa.</p>



<p class="wp-block-paragraph">Via Carpatia je medzinárodný dopravný koridor, ktorý má spojiť sever a juh Európy, od litovskej Klaipėdy po grécky Solún. Jeho poľská časť má mať približne 700 kilometrov a zahŕňa úseky rýchlostných ciest S61, S16 a S19. Smeruje od hraničného priechodu Budzisko na hranici s Litvou po Barwinek pri Slovensku. Práve na S19 má na slovenskej strane nadviazať rýchlostná cesta R4.</p>



<h2 class="wp-block-heading">Pri Białystoku spojili S19 s cestou S8</h2>



<p class="wp-block-paragraph">Motoristi môžu od 20. októbra 2026 využívať úsek Krynice &#8211; Dobrzyniewo &#8211; Białystok Zachód dlhý približne 10,2 kilometra. Nová cesta prepája S19 s rýchlostnou cestou S8 a stane sa súčasťou severozápadného obchvatu Białystoku.</p>



<p class="wp-block-paragraph">Úsek má dve vozovky, každú s dvoma jazdnými pruhmi a odstavným pruhom. Súčasťou investície boli štyri mosty, osem nadjazdov a dvanásť priechodov pre živočíchy. Konzorcium spoločností PORR a Unibep ho realizovalo v režime naprojektuj a postav za 405,6 milióna zlotých.</p>



<p class="wp-block-paragraph">Na severovýchode Poľska pribudlo aj spojenie Kuźnica &#8211; Sokółka Północ, sprejazdňované postupne v rokoch 2025 a 2026. Celkovo ide o približne 15,9 kilometra, z ktorých 10,6 kilometra tvorí rýchlostná cesta a 5,3 kilometra cesta triedy GP. Kuźnica leží pri hranici s <strong>Bieloruskom</strong>, nie s Litvou.</p>



<h2 class="wp-block-heading">Najvyššia estakáda má piliere vysoké 80 metrov</h2>



<p class="wp-block-paragraph">Podstatne náročnejšia je výstavba na juhu Poľska. V Podkarpatskom vojvodstve musí S19 prekonať členitý terén, hlboké údolia a geologicky komplikované územie.</p>



<p class="wp-block-paragraph">Medzi obcami Żarnowa a Godowa na úseku Babica &#8211; Jawornik vzniká estakáda ES-26. Tvoria ju dve samostatné súbežné mostné konštrukcie. Objekt bude dlhý <strong>1 082 metrov</strong>, široký 29 metrov a jeho najvyššie piliere dosahujú <strong>80 metrov</strong>. Najdlhšie rozpätie má 188 metrov.</p>



<p class="wp-block-paragraph">GDDKiA 27. októbra 2026 oznámila dokončenie betónovania nosnej konštrukcie vozovky v smere na Barwinek. Ďalšia etapa sa sústredí na konštrukciu pre opačný smer, na Rzeszów. Hotová prvá časť má uľahčiť dopravu betónu.</p>



<p class="wp-block-paragraph">Na podpery sa spotrebovalo 51 800 kubických metrov betónu a 9 250 ton ocele. Celková rozpracovanosť 11,6-kilometrového úseku Babica &#8211; Jawornik podľa októbrovej správy prekročila 80 percent. Zhotoviteľom je spoločnosť Intercor.</p>



<figure class="wp-block-gallery has-nested-images columns-default is-cropped wp-block-gallery-1 is-layout-flex wp-block-gallery-is-layout-flex">
<figure class="wp-block-image size-large"><img fetchpriority="high" decoding="async" width="1024" height="683" data-id="4848" src="https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-1024x683.jpg" alt="Estakáda pri obci Zarnowa. Foto: GDDKiA" class="wp-image-4848" srcset="https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-1024x683.jpg 1024w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-300x200-1.jpg 300w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-768x512.jpg 768w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-150x100.jpg 150w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-1536x1024.jpg 1536w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-324x216.jpg 324w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-696x464.jpg 696w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada-1068x712.jpg 1068w, https://www.doprava.org/wp-content/uploads/2026/11/s19-estakada.webp 1800w" sizes="(max-width: 1024px) 100vw, 1024px" /><figcaption class="wp-element-caption">Estakáda pri obci Zarnowa. Foto: GDDKiA</figcaption></figure>
</figure>



<h2 class="wp-block-heading">Náročná je aj doprava betónu na stavenisko</h2>



<p class="wp-block-paragraph">Pri výstavbe estakád predstavuje veľkú výzvu samotný prístup k jednotlivým podporám. Technologické cesty v okolí ES-26 prekonávajú výškový rozdiel až 120 metrov a ich sklon miestami dosahuje 15 percent. Domiešavače preto nemôžu jazdiť s plným nákladom. Podľa GDDKiA sa ich kapacita využíva najviac na 80 percent.</p>



<p class="wp-block-paragraph">Estakády tvoria približne 30 percent úseku Babica &#8211; Jawornik. Náročné je aj ich zakladanie: niektoré pilóty majú priemer 1,5 metra a dosahujú hĺbku až 42,5 metra.</p>



<p class="wp-block-paragraph">Nosná konštrukcia ES-26 vzniká technológiou letmej betonáže. Jednotlivé segmenty sa postupne budujú z pilierov na obe strany, až sa susedné časti spoja. Tento postup umožňuje pracovať vysoko nad údolím bez podopretia konštrukcie lešením zo zeme.</p>



<figure class="wp-block-gallery has-nested-images columns-default is-cropped wp-block-gallery-2 is-layout-flex wp-block-gallery-is-layout-flex">
<figure class="wp-block-image size-large"><img decoding="async" width="1024" height="683" data-id="4849" src="https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-1024x683.jpg" alt="Najvyššia estakáda v Poľsku na ceste S19. Foto: GDDKiA" class="wp-image-4849" srcset="https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-1024x683.jpg 1024w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-300x200-1.jpg 300w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-768x512.jpg 768w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-150x100.jpg 150w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-324x216.jpg 324w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku-696x464.jpg 696w, https://www.doprava.org/wp-content/uploads/2026/11/s19babica-jawornik-estakadaes-najvyssia-estakada-v-polsku.jpg 1068w" sizes="(max-width: 1024px) 100vw, 1024px" /><figcaption class="wp-element-caption">Najvyššia estakáda v Poľsku na ceste S19. Foto: GDDKiA</figcaption></figure>
</figure>



<h2 class="wp-block-heading">Pri Jaworniku pripravujú takmer trojkilometrový tunel</h2>



<p class="wp-block-paragraph">Ďalším náročným úsekom bude Jawornik &#8211; Lutcza. GDDKiA v januári 2026 oznámila podanie žiadosti o rozhodnutie ZRID, ktoré umožňuje realizáciu cestnej stavby. V tom čase išlo o posledný úsek Via Carpatia v Podkarpatskom vojvodstve čakajúci na toto povolenie.</p>



<p class="wp-block-paragraph">Hoci bude mať iba 5,25 kilometra, jeho súčasťou bude <strong>2,8 kilometra dlhý dvojrúrový tunel pod vrchom Kamieniec</strong>. Pôjde o najdlhší z troch plánovaných tunelov S19 v tomto vojvodstve. Do tunela bude cesta vstupovať z 815 metrov dlhej estakády s piliermi vysokými až 36 metrov.</p>



<p class="wp-block-paragraph">Zhotoviteľom je konzorcium Gülermak a Budimex. Hodnota zákazky presahuje 1,9 miliardy zlotých a podľa zverejneného harmonogramu sa dokončenie plánuje na rok <strong>2031</strong>.</p>



<h2 class="wp-block-heading">V Lubelskom vojvodstve pribudla ďalšia povolená stavba</h2>



<p class="wp-block-paragraph">Postupuje aj výstavba severne od Lublinu. Úsek Międzyrzec Podlaski &#8211; Radzyń Podlaski získal rozhodnutie ZRID v apríli 2026. Približne 22,3 kilometra dlhej stavbe sa tak otvorila cesta k realizácii.</p>



<p class="wp-block-paragraph">GDDKiA pri vydaní povolenia uviedla, že všetkých šesť úsekov medzi hranicou Mazovského a Lubelského vojvodstva a Lublinom, spolu približne 100 kilometrov, už vstúpilo do výstavby. Nejde teda o celú Via Carpatia v Lubelskom vojvodstve, ale o jej severnú časť.</p>



<p class="wp-block-paragraph">Úsek Międzyrzec Podlaski &#8211; Radzyń Podlaski realizuje spoločnosť Stecol Corporation za viac ako 570,7 milióna zlotých. Sprejazdnenie sa plánuje v roku 2028.</p>



<h2 class="wp-block-heading">Domaradz &#8211; Krosno zabrzdil spor so zhotoviteľom</h2>



<p class="wp-block-paragraph">Nie všetky stavby postupujú podľa plánu. GDDKiA 14. mája 2026 oznámila odstúpenie od zmluvy so spoločnosťou Mostostal Warszawa na úseku Domaradz &#8211; Krosno.</p>



<p class="wp-block-paragraph">Podľa cestárskej správy dosahovala rozpracovanosť kontraktu iba <strong>13 percent, hoci uplynulo 96 percent času na jeho realizáciu</strong>. Investor poukázal na meškanie, projektové zmeny nezlučiteľné s environmentálnym rozhodnutím a nepokračovanie v prácach napriek výzve.</p>



<p class="wp-block-paragraph">Mostostal Warszawa už predtým oznámil vlastné odstúpenie od zmluvy, pričom argumentoval okrem iného nepredvídanými podmienkami podložia a potrebou predĺžiť mostné objekty. GDDKiA jeho odstúpenie označila za neúčinné.</p>



<p class="wp-block-paragraph">Po ukončení kontraktu cestárska správa avizovala zabezpečenie a inventarizáciu staveniska, následne prípravu nového verejného obstarávania. Nový zhotoviteľ má dostať existujúce povolenie a projektovú dokumentáciu, na ktorých bude môcť založiť pokračovanie výstavby.</p>



<figure class="wp-block-gallery has-nested-images columns-3 is-cropped wp-block-gallery-3 is-layout-flex wp-block-gallery-is-layout-flex">
<figure class="wp-block-image size-large"><img decoding="async" width="1024" height="683" data-id="4850" src="https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-1024x683.jpg" alt="" class="wp-image-4850" srcset="https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-1024x683.jpg 1024w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-300x200-1.jpg 300w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-768x512.jpg 768w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-150x100.jpg 150w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-324x216.jpg 324w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26-696x464.jpg 696w, https://www.doprava.org/wp-content/uploads/2026/11/estakada-s26.jpg 1068w" sizes="(max-width: 1024px) 100vw, 1024px" /><figcaption class="wp-element-caption">Estakáda ES26. Foto: GDDKiA</figcaption></figure>
</figure>



<h2 class="wp-block-heading">Výstavbu podporujú európske fondy</h2>



<p class="wp-block-paragraph">Významnú časť financovania zabezpečuje Európska únia prostredníctvom programu FEnIKS na obdobie 2021 &#8211; 2027, zameraného na infraštruktúru, klímu a životné prostredie.</p>



<p class="wp-block-paragraph">GDDKiA v septembri 2026 oznámila podporu <strong>viac ako dve miliardy zlotých</strong> na projekt zahŕňajúci 44,5 kilometra S19 v Podkarpatskom vojvodstve. Celková hodnota projektu dosahuje 4,4 miliardy zlotých. Zahŕňa úseky Babica &#8211; Jawornik, Domaradz &#8211; Krosno, Krosno &#8211; Miejsce Piastowe a Miejsce Piastowe &#8211; Dukla. Posledné dva z nich sú podľa správy dostupné motoristom už od decembra 2025.</p>



<p class="wp-block-paragraph">Poľská S19 sa postupne mení na súvislé severojužné spojenie. Otvorenie jednotlivých úsekov však ešte neznamená dokončenie celého koridoru. Rozhodujúce bude prepojenie zostávajúcich stavieb vrátane náročných tunelových úsekov a pokračovanie cez slovenskú R4.</p>



<figure class="wp-block-embed is-type-video is-provider-youtube wp-block-embed-youtube wp-embed-aspect-16-9 wp-has-aspect-ratio"><div class="wp-block-embed__wrapper">
<div class="youtube-embed" data-video_id="dGX48Fx6G7s"><iframe loading="lazy" title="Najwyższa estakada w Polsce na półmetku budowy!" width="696" height="392" src="https://www.youtube.com/embed/dGX48Fx6G7s?feature=oembed&#038;enablejsapi=1" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture; web-share" referrerpolicy="strict-origin-when-cross-origin" allowfullscreen></iframe></div>
</div></figure>



<h2 class="wp-block-heading"><strong>Zdroje:</strong></h2>



<ul class="wp-block-list">
<li><a href="https://www.gov.pl/web/gddkia-bialystok/dwie-eski-polaczone-kolo-bialegostoku?utm_source=chatgpt.com">GDDKiA: Prepojenie S19 a S8 pri Białystoku</a></li>



<li><a href="https://www.gov.pl/web/gddkia/najwyzsza-estakada-w-polsce-na-polmetku-budowy?utm_source=chatgpt.com">GDDKiA: Najvyššia estakáda v Poľsku v polovici výstavby</a></li>



<li><a href="https://www.gov.pl/web/gddkia/wyzwania-na-budowie-s19-babica--jawornik?utm_source=chatgpt.com">GDDKiA: Výzvy na stavbe S19 Babica &#8211; Jawornik</a></li>



<li><a href="https://www.gov.pl/web/gddkia/domykamy-szlak-via-carpatia?utm_source=chatgpt.com">GDDKiA: Príprava úseku Jawornik &#8211; Lutcza</a></li>



<li><a href="https://www.gov.pl/web/gddkia-kielce/mozemy-budowac-kolejny-odcinek-trasy-via-carpatia?utm_source=chatgpt.com">GDDKiA: Povolenie pre úsek Międzyrzec Podlaski &#8211; Radzyń Podlaski</a></li>



<li><a href="https://www.gov.pl/web/gddkia-rzeszow/umowa-na-s19-domaradz--krosno-rozwiazana-z-winy-wykonawcy?utm_source=chatgpt.com">GDDKiA: Ukončenie zmluvy na úsek Domaradz &#8211; Krosno</a></li>



<li><a href="https://www.gov.pl/web/gddkia/wsparcie-ue-dla-budowy-drog-ekspresowych-s11-i-s19?utm_source=chatgpt.com">GDDKiA: Európske financovanie ciest S11 a S19</a></li>
</ul>
<p>Článok <a href="https://www.doprava.org/poliaci-dokoncuju-cestu-via-carpatia-pozrite-sa-ako-vyzera/">Poliaci dokončujú cestu Via Carpatia. Pozrite sa, ako vyzerá</a> je zobrazený ako prvý na <a href="https://www.doprava.org">Doprava.org</a>.</p>